Adjusting Issue Estimate When Logging Work

Adjusting Issue Estimate When Logging Work

When entering a work log you can also adjust remaining estimate using one of 4 modes. This is exactly the same with JIRA's own "Log Work" dialog, but we are explaining here again.

  • Adjust Automatically: The estimate will be reduced by the amount of work done, but it will never be below 0
  • Use Existing Estimate: Remaining estimate is kept unchanged.
  • Set To: Allows you to freely specify a new remaining estimate
  • Reduce By: Remaining estimate is reduced by the specified value

More details of entering work log can be found here in JIRA's own documentation and nearly all of them are also valid for log work dialog of WorklogPRO too.

You can also hide Remaining estimate field group and reduce log work dialog height. Your preference will be remembered and when you open the dialog next time.

Related content

Issue Filters on Work Log Dialog
Issue Filters on Work Log Dialog
Read with this
Logging Work for Multiple Issues
Logging Work for Multiple Issues
Read with this
Logging Work to Issues
Logging Work to Issues
Read with this
Getting Notification When an Issue's Time Spent is Close to Original Estimate
Getting Notification When an Issue's Time Spent is Close to Original Estimate
Read with this