How Sub-task Remaining Estimates Affect Parent Issues

How Sub-task Remaining Estimates Affect Parent Issues

The remaining estimate of a parent issue is calculated based on the remaining estimates of its sub-tasks. Updates to the parent issue occur only when there is a change in a sub-task’s remaining estimate. In certain cases, logging work on a sub-task does not affect the parent issue’s remaining estimate. The scenarios below describe when and why this behavior occurs.

Scenario 1: Sub-task Remaining Estimate Is Already 0

If a sub-task’s Remaining Estimate is already set to 0, logging additional work on that sub-task does not reduce the parent issue’s Remaining Estimate.

Since there is no remaining time left on the sub-task, WorklogPRO has no remaining estimate to deduct from the parent issue. As a result, the parent issue’s remaining estimate remains unchanged.

Scenario 2: Work Logged Using “Use Existing Estimate”

When work is logged on a sub-task using the “Use existing estimate” option and the remaining estimate is not adjusted:

  • The sub-task’s Remaining Estimate stays the same.

  • Because there is no change in the sub-task’s remaining estimate, the parent issue’s Remaining Estimate also remains unchanged.

In short, the parent Remaining Estimate is updated only when the sub-task’s Remaining Estimate is reduced. If the sub-task remaining time is already 0 or is not changed during work logging, the parent remaining time will stay the same.